28 August 2015 ~ 7 Comments

Project Advancement | August 28 – September 7

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Installation of dewatering […]

Continue Reading

28 August 2015 ~ 0 Comments

Featured Photos – August 27

The Central Subway Community Advisory Group (CAG) and community members learn more about the upcoming 4th & King trackway work. The meeting was held at the Creamery in SOMA. Crews are preparing for the upcoming trackway work which will take place starting 10 p.m., Friday, September 4 through early morning, Tuesday, September 8. During construction […]

Continue Reading

21 August 2015 ~ 7 Comments

Project Advancement | August 21 – 31

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Installation of dewatering […]

Continue Reading

20 August 2015 ~ 1 Comment

Featured Photos – August 20

Work is being done to upgrade utilities for the station platform at 4th & Brannan streets. Workers replace old water and sewer pipes on 4th Street between Townsend and King streets prior to the installation of track for the new surface portion of the Central Subway alignment. Crews wrap utility work at 4th & King […]

Continue Reading

14 August 2015 ~ 1 Comment

Project Advancement |August 14 – 24

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Construction schedules, bus […]

Continue Reading

14 August 2015 ~ 0 Comments

Featured Photos – August 13

Upcoming Labor Day Weekend (10 p.m., Friday, September 4 to 5 a.m., Tuesday, September 8) work at 4th & King includes installation of transit signal priority equipment as well as track improvements for the future Central Subway extension of the T Third Line. Traffic will be impacted due to construction as well as weekend activities. […]

Continue Reading

11 August 2015 ~ 0 Comments

Chinatown Dewatering Work

Construction on the Central Subway project continues in Chinatown. We started installing dewatering wells along Stockton Street between Sacramento and Jackson.   This is in preparation for the Chinatown Station.  The purpose of the wells is to remove water from solid material when excavation is being performed in the near future.   The contractor will dig approximately […]

Continue Reading

07 August 2015 ~ 2 Comments

Project Advancement l August 7 – 17

Central Subway | Project Advancement August 7 – August 17, 2015 This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, […]

Continue Reading

05 August 2015 ~ 0 Comments

Featured Photos – August 5

Utility relocation work is underway at the intersection of Washington and Stockton streets. Workers move welding equipment for the construction of temporary supports in the station entrance structure. Temporary supports, also known as walers, are installed prior to the construction of the finished walls. Want to see more photos of project construction?  Check out our Flickr, […]

Continue Reading

03 August 2015 ~ 2 Comments

Upcoming work at 4th and King

Heads up! Construction work at 4th & King is slated for Labor Day Weekend, September 4 through 7. This will be a two-phase project for signal installation and track enhancement. Below is the area where work will take place. Over the Labor Day Weekend, the T Third Line rail service will still run, but Muni […]

Continue Reading