Archive | February, 2016

26 February 2016 ~ 2 Comments

Project Advancement | February 26 – March 7

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Starting Monday night, […]

Continue Reading

25 February 2016 ~ 0 Comments

Featured Photos – February 25

A temporary structure for rebuilding the roof of the south east corner of the Union Square Garage. This will be the future site of the north entrance to the Union Square|Market Street Station. Demolition work at the south east corner of the Union Square Garage. A view from inside the north concourse, north of Geary […]

Continue Reading

19 February 2016 ~ 0 Comments

Project Advancement | February 19 – 29

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Construction of the […]

Continue Reading

12 February 2016 ~ 1 Comment

Project Advancement | February 12 – 22

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Now through March, […]

Continue Reading

11 February 2016 ~ 0 Comments

Featured Photos – February 11

This is the top level of the “station box,” the structure beneath 4th Street between Folsom and Howard where trains will stop to take on passengers.  When completed, the station box will house the train platform area and infrastructure for station operations. In the lower level of the station box, welding work illuminates a work […]

Continue Reading

10 February 2016 ~ 0 Comments

Project Advancement | February 5 – 15

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Construction activity at […]

Continue Reading

10 February 2016 ~ 0 Comments

Project Advancement | January 29 – February 8

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Construction continues to […]

Continue Reading

05 February 2016 ~ 0 Comments

Project Advancement | January 22 – February 1

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Through Friday, February […]

Continue Reading

05 February 2016 ~ 0 Comments

Project Advancement | January 15 – 25

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Construction at all […]

Continue Reading