Project Advancement I April 15 – April 25

Construction of the Yerba Buena|Moscone Station mezzanine floor is underway.

Construction of the Yerba Buena|Moscone Station mezzanine floor is underway

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown.

Installation of 36” and 48” sewer lines on the east side of 4th Street between Bryant Street and King Street begins on Monday, April 18. Hours of construction are 7a.m. to 4p.m. Two lanes of traffic will be open on the west side of 4th Street. Parking will be restricted on both sides of 4th Street.

Construction schedules, bus routes, and stop locations are subject to change due to unforeseen conditions. Signs will be posted at affected stops to advise of service changes.

Our thanks go out to the businesses, residents, shoppers, commuters, and all those who are touched by the Project, for their continued engagement as we work to extend the city’s public transportation system.
The Central Subway Team