Archive | Construction Update

13 April 2011 ~ Comments

New Tow-Away Hours on Stockton Street

Effective April 16, 2011, the tow-away hours and days will be changed along the east side of Stockton Street between Post and Campton streets.
The SFMTA Parking  will be bagging meters on Thursday morning, April 14 and remove the bags by the close of business on Friday, April 15. The Sign Shop will swap out the [...]

Continue Reading

25 March 2011 ~ Comments

Construction Schedule Mar. 26 to Apr. 15

Central Subway Construction Look Ahead
March 26, 2011 to April 15, 2011
(PDF available: Contract 1251 March 26-April 15 Look Ahead)
Utility Relocation for the Union Square/Market Street Station

Geary Street (east and west side of Stockton Street): Continuation of sewer installation
Geary Street (east side of Stockton Street): Excavation of high pressure water line

O’Farrell Street (east and west [...]

Continue Reading

10 March 2011 ~ Comments

Construction Schedule Mar. 7 – Mar. 25

Central Subway Construction Look Ahead
March 7, 2011 to March 25, 2011
(PDF available: Contract 1251 March 7 Look Ahead)
Utility Relocation for the Union Square/Market Street Station

Geary Street (east and west side of Stockton Street): Continuation of sewer installation

O’Farrell Street (east and west side of Stockton Street): Continuation of sewer installation
East side of Stockton Street (Geary to [...]

Continue Reading

08 March 2011 ~ Comments

Union Square Utility Relocation Update

Utility relocation for the Union Square/Market Street Station has been underway for over a month and you’ve likely seen Synergy Project Management working along Stockton Street and the adjacent sections of side streets on Geary and O’Farrell streets. They are currently digging in the middle of the streets to install sewer lines and working under [...]

Continue Reading

23 February 2011 ~ Comments

Construction Schedule Feb. 21-Mar. 6

Central Subway Construction Look Ahead
February 21, 2011 to March 6, 2011
(PDF available: Contract 1251 Feb. 21 Look Ahead)
Utility Relocation for the Union Square/Market Street Station

Geary Street (east and west side of Stockton Street): Continuation of sewer installation

O’Farrell Street (east and west side of Stockton Street): Continuation of sewer installation
East side of Stockton Street (Geary to O’Farrell [...]

Continue Reading

08 February 2011 ~ Comments

Utility Relocation Construction Schedule

Central Subway Construction Look Ahead
February 9, 2011 to February 21, 2011
(PDF available: Central Subway Feb 9 Look Ahead)
Upcoming Major Work

Geary Street: Potholing and Sewer
O’Farrell Street: Potholing and Sewer
East side of Stockton Street (Geary to O’Farrell): Construction of barriers and demolition of sidewalk

Construction is scheduled for seven days a week from 7 a.m. to 7 p.m., [...]

Continue Reading

31 January 2011 ~ Comments

Traffic Detour in Union Square (update)

Underground utility relocation construction for the future Union Square/Market Street Central Subway station is set to begin on Monday. Traffic traveling south on Stockton Street during utility relocation activities will be directed to use alternative routes.  The detour routes are available to help guide you through the area.
There will be one lane open [...]

Continue Reading

02 December 2010 ~ Comments

Later Construction Hours until Dec. 17

For the next 2 weeks, expect delays along Fourth Street and please take alternative routes when possible.  Utility relocation has been extended approximately until 5:30p.m.  and additional construction activities will occur on Saturdays (Dec. 4 and Dec. 11).  Construction activities will stop from Dec. 20 through Dec. 31 but will resume [...]

Continue Reading

09 November 2010 ~ Comments

Stuck in the Midden with You

Recently, during the course of excavating for utility relocation for the Moscone Station, workers came across deposits of shells in the trenches located on Fourth Street between Howard and Folsom streets. Upon discovering these deposits, Mike Stoyka, an archaeologist assigned to watch over the trenching, declared that these could be possible middens and needed to [...]

Continue Reading

09 July 2010 ~ Comments

Recap of Water Main Line

Here’s an update from this morning’s incident at the construction site at Fourth and Bryant streets. A water main line broke at Fourth and Bryant streets sending a geyser of water shooting 30 feet up in the air.
As of 2:15pm, repairs on the water main line have been completed and water service is back on.
At approximately 9:00am [...]

Continue Reading