Archive | Stations

01 November 2013 ~ 0 Comments

Construction Update | November 2-11

Beneath 4th Street, segments of the new subway tunnels are delivered underground. Our first tunnel boring machine, Mom Chung, has now built about 1,400 feet of tunnel. During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station construction is continuing in […]

Continue Reading

25 October 2013 ~ 0 Comments

Construction Update | October 26-November 4

On Stockton Street, we are beginning to restore the construction zone. We plan to reopen the road to traffic in November for the holiday season. During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station construction is continuing in Chinatown and […]

Continue Reading

27 September 2013 ~ 0 Comments

Construction Update | Sept. 28-Oct. 7

The Pagoda Palace site this week, after our crews completed demolishing the former theater. During the next 10 days, tunneling and tunneling preparatory work will continue in southern SoMa, Union Square and North Beach. Work to prepare for station construction is continuing in Chinatown and northern SoMa. For descriptions of construction impacts in each neighborhood, […]

Continue Reading

24 May 2013 ~ 0 Comments

SFMTA awards Central Subway’s largest and final major construction contract

Construction of the Union Square/Market Street Station, shown here, is included in the major contract awarded earlier this week. This week the SFMTA awarded the contract to construct the Central Subway’s stations, train tracks and operating systems to California-based firm Tutor Perini. Tutor Perini’s bid of $840 million was the lowest of three bids received […]

Continue Reading