Archive | Union Square/Market Street

03 December 2015 ~ 0 Comments

Featured Photos – December 3

Union Square Business Improvement District (BID) Executive Director Karin Flood and Central Subway Program Director John Funghi kick-off the second annual Winter Walk. This pop-up open space, features entertainment, Off the Grid food trucks, and is located on Stockton Street between Geary and Ellis during the holiday moratorium. The much-appreciated plaza features a nightly light […]

Continue Reading

20 November 2015 ~ 2 Comments

Project Advancement | November 20 – 30

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. With the holiday […]

Continue Reading

13 November 2015 ~ 0 Comments

Project Advancement | November 13 – 23

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. The second phase […]

Continue Reading

30 October 2015 ~ 5 Comments

Project Update | October 30 through November 9

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. The second phase […]

Continue Reading

23 October 2015 ~ 0 Comments

Project Update | October 23 through November 3

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. The second phase of […]

Continue Reading

22 October 2015 ~ 0 Comments

Featured Photos – October 22

Construction of the North Concourse at the future site of the Union Square/Market Street Station. Crews build a new ramp inside the Union Square Garage located at the southeast corner of Union Square. Work is taking place on all four levels of the garage.  This work includes laying rebar, constructing concrete forms and building a […]

Continue Reading

16 October 2015 ~ 0 Comments

Project Update | October 16 – October 26

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. The second phase […]

Continue Reading

09 October 2015 ~ 2 Comments

Project Advancement | October 9 – October 19

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. There’s much activity […]

Continue Reading

02 October 2015 ~ 16 Comments

Project Advancement | October 2 -12

  This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Tutor Perini […]

Continue Reading

25 September 2015 ~ 0 Comments

Project Advancement | September 25 – October 5

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. For the surface […]