15 June 2012 ~ 10 Comments

Construction Update: Launch box and headwall construction proceeding in SoMa, road restoration progressing in Union Square

Construction at the site of the tunnel launch box, shown here, ramped up this week.  Construction to prepare for the Central Subway tunnel ramped up this week, and the new sidewalks on the west side of Stockton Street are almost completely restored. Here’s what to expect in the next three weeks as tunnel preparation continues and the Union […]

Continue Reading

11 June 2012 ~ 3 Comments

Starting in SoMa: On 4th Street between Folsom and Howard, construction to prepare for tunneling

Construction is now underway on 4th Street near the intersection with Folsom Street. Construction to prepare for the installation of below-ground walls, called headwalls, has begun on 4th Street between Folsom and Howard streets, the site of the future Yerba Buena/Moscone Station. The work currently underway includes potholing and utility relocation. Headwall installation, which involves major […]

Continue Reading

06 June 2012 ~ 4 Comments

New sidewalks on Stockton Street as utility work nears completion

Since breaking ground in January 2011, contractor Synergy Project Management has finished relocating a variety of utility lines around Union Square to prepare for construction of the Union Square/Market Street Station. Now, with much of this work complete, sidewalks are being restored and reopened for pedestrians. Check out these pictures of the beautiful new sidewalks […]