Project Advancements | September 6 – September 15, 2014

On Stockton Street near Ellis Street, the future Union Square/Market Street station is being constructed.

On Stockton Street near Ellis Street, the future Union Square/Market Street station is being constructed.

During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This post contains brief updates about what is happening in each neighborhood. For more detailed information, click here or on the links below. You can also find construction, traffic detour, and Muni impact information on our project Google Map. For safety reasons, we encourage the public to follow all traffic and pedestrian notifications posted at the work sites.

Southern SoMa (Harrison to King/Berry)Excavation of a sewer man-hole continues on Freelon and 4th Street. Excavation of an AT&T vault to start on 4th and Bryant. Near Bluxome Street, installation of an AT&T vault to start. On Bryant Street, west of 4th Street, sewer installation to start next week. Temporary walkways are in place around the construction zones.

Northern SoMa (Market to Harrison)At 4th and Folsom, work to build the Yerba Buena/Moscone Station continues. This includes construction of the station walls within the work site and water line replacement at the intersection of 4th and Folsom. 4th Street from Howard to Folsom streets are reduced to one traffic lane until 5 a.m., Monday, September 8. Starting Monday, September 15, traffic lanes on 4th Street between Howard and Folsom will be reduced to one lane until early November.

Union SquareStockton Street between Ellis and Geary is closed to vehicular traffic to allow for construction of the Union Square/Market Street Station. Work is underway for pile installation to construct the station walls.

Pile installation takes place at the southwest intersection of Stockton and O’Farrell streets until late September. One lane of travel will be open. Sidewalk closure is to take place overnight between 10 p.m. and 6 a.m. on the northeast corner of Stockton at O’Farrell for next three weeks. Expect delays and use alternative routes.

Muni service impact:
The bus stop at Geary and Stockton will be temporarily discontinued until late September. Please board bus on Geary at Powell. Check back on the weekly Construction Update for the most current information on the re-opening of this stop.

Chinatown:  The contractor started station wall construction at the future station site at Stockton and Washington streets and the adjacent section of Washington Street. Work to replace the water pipeline and install a new fire hydrant on Washington is ongoing.

North Beach: Work continues at 1731-1741 Powell. Street restoration has been completed on Columbus Avenue between Filbert and Union. Sustainable Streets is scheduled to install new street lights and landscaping in the median on this portion of Columbus Avenue. This work will be completed by the end of 2014.

We thank the businesses, residents, shoppers, and commuters of San Francisco for their continued engagement with this significant investment in the extension of our public transportation system.