Archive | March, 2012

30 March 2012 ~ 1 Comment

Construction Update: Utility Work on 4th Street between Harrison and Bryant

An excavator at the construction site on 4th Street. Work to demolish and relocate utility lines has commenced along 4th Street between Harrison and Bryant streets. The purpose of this work is to prepare the Central Subway alignment for construction of a launch box at the site where the tunnel boring machines will begin tunneling. […]

Continue Reading

23 March 2012 ~ 0 Comments

Construction Update: Wrap, drilling complete; utility relocation continues

Paving O’Farrell Street. Since our last construction update, Central Subway contractors have continued to make progress, completing the following work: Drilling operations around Union Square to collect information about the chemical conditions of soil and groundwater Installation of a decorative wrap at 933 to 949 Stockton Street, the future site of the Chinatown Station Installation of […]

Continue Reading

16 March 2012 ~ 2 Comments

Mayor Lee, local leaders unveil decorative wrap at Chinatown Station site

Mayor Lee spoke about the benefits of the Central Subway today at a press conference in Chinatown. The Central Subway will improve public transportation in San Francisco, create thousands of jobs and enhance the quality of life of residents and visitors alike. That’s what Mayor Edwin M. Lee and other local leaders and community members […]

Continue Reading

02 March 2012 ~ 0 Comments

Construction Schedule: March 3-23

Utility relocation work around Union Square. Feb. 11 – March 2, 2012. Crews are continuing to relocate utility lines around Union Square to prepare the project alignment for the Union Square/Market Street Station. We expect all utility relocations around Union Square to be completed by June 2012. The complete, current three-week construction schedule for Union Square […]

Continue Reading