26 November 2012 ~ 0 Comments

Photos: Union Square, North Beach construction sites restored for holiday season

Last week Central Subway crews restored portions of Stockton Street and Ellis Street in Union Square and Columbus Avenue in North Beach to prepare for a holiday season construction pause. On these blocks, roadways and pedestrian walkways were returned to their regular use in time for Thanksgiving. Check out these photos of restoration in progress […]

Continue Reading

20 November 2012 ~ 1 Comment

Central Subway Project awarded $85 million in New Starts funds

When the Central Subway is complete, T Third Line trains will continue straight at the intersection of 4th and King streets instead of turning right onto King Street. The U.S. Department of Transportation recently awarded $85 million in federal funding to the Central Subway Project. The funding, from the Federal Transit Administration’s New Starts program, […]

Continue Reading

19 November 2012 ~ 2 Comments

Construction Update: Central Subway construction during the holiday season

This construction site near Union Square will be restored and reopened to traffic during the holiday season. During the holiday season, construction at some currently active Central Subway construction sites will pause, with roadways and pedestrian walkways restored to regular use. At other sites, construction will continue. This blog post provides a summary of construction […]

Continue Reading

09 November 2012 ~ 1 Comment

Construction update: New traffic configuration starting in North Beach, full closure of 4th Street implemented under I-80 overpass

Construction at the site where tunneling will begin next year. Along the Central Subway Project alignment, tunnel pre-construction has continued to progress at the four active construction sites. Since our last update, crews have completed construction of a sewer manhole and a sewer line in North Beach, and a portion of 4th Street has closed […]