Archive | construction

09 July 2010 ~ Comments

Recap of Water Main Line

Here’s an update from this morning’s incident at the construction site at Fourth and Bryant streets. A water main line broke at Fourth and Bryant streets sending a geyser of water shooting 30 feet up in the air.
As of 2:15pm, repairs on the water main line have been completed and water service is back on.
At approximately 9:00am [...]

Continue Reading

21 May 2010 ~ Comments

CTC awards the Central Subway $27M

The Central Subway Project received great news this week! The project has been awarded $27 million in tunnel component funds from the California Transportation Commission (CTC).  These funds are awarded for the Central Subway’s future connection to the California High Speed Rail that is currently in planning.  The route of the High Speed Rail is [...]

Continue Reading

11 May 2010 ~ Comments

Geotechnical Drilling is on Schedule

Contrary to the Examiner article “Central Subway behind schedule,” dated 5/11/10 and written by Katie Worth, the Central Subway Project boring operation is not behind schedule.  The schedule for this segment, geotechnical drilling, of the project was rearranged to accommodate concurrent on-going utility relocation activities.  This is simply an example of contractors working together and [...]

Continue Reading

07 May 2010 ~ Comments

Updated May 2010 Drilling Schedule

There have been changes to the drilling schedule!  Please read the following notice and the dates in red are the new scheduled days for drilling.
The San Francisco Municipal Transportation Agency and PB/Telamon with Treadwell & Rollo will continue drilling operations for supplemental geotechnical investigations; the purpose of which are to provide critical geotechnical and hydro-geologic [...]

Continue Reading

30 April 2010 ~ Comments

Drilling Notice: May 2010

The San Francisco Municipal Transportation Agency and PB/Telamon with Treadwell & Rollo will continue drilling operations for supplemental geotechnical investigations; the purpose of which are to provide critical geotechnical and hydro-geologic information needed for final design and pre-construction of the proposed subway tunnel and associated structures.
Here’s the anticipated drilling [...]

Continue Reading

23 April 2010 ~ Comments

Important re-route information

For those of you who haven’t heard about the re-routing on the 30 Stockton and 45 Union/Stockton, here’s an update!
This re-route is required due to ongoing utilities relocation and underpinning work at 401 Fourth Street to shore up the foundation.
The 30 Stockton and 45 Union/Stockton are being re-routed, while the street is not [...]

Continue Reading

26 March 2010 ~ Comments

Utility Relocation on the move…

Synergy Project Management began the installation of sewer line and manholes along Clementina between Fourth and Fifth streets.
Traffic is being re-routed while sewer work is being performed on Clementina Street.  Clementina Street will be closed during the actual work period, Monday-Friday from 7:00 a.m.-3:00 p.m.

A detour sign has been posted at Clementina and Fifth [...]

Continue Reading

15 March 2010 ~ Comments

Utilities Relocation Progress

Synergy’s work on utilities relocation is moving along. The installation of sewer and low pressure water lines, excavation for joint trench and dry utility vaults are ongoing at various locations. Phoenix Electric (subcontractor) has begun laying conduits for the joint trenches along various locations within the route. The coring through the Moscone Center wall [...]

Continue Reading

09 March 2010 ~ Comments

Drilling Notice: March 10-15, 2010

The Central Subway Project will begin drilling operations for supplemental geotechnical investigations in your neighborhood. From March 10-15, 2010, drilling will be on Fourth and Harrison streets. We sincerely apologies for any inconvenience  this may cause you. Please review this flyer for more information regarding construction work hours and duration of this project. If you [...]

Continue Reading

05 March 2010 ~ Comments

Supplemental Geotechnical Schedule

The San Francisco Municipal Transportation Agency and PB/Telamon with Treadwell & Rollo has begun drilling operations for supplemental geotechnical investigations; the purpose of which are to provide critical geotechnical and hydro-geologic information needed for final design and pre-construction of the proposed subway tunnel and associated structures.
Here’s the anticipated drilling schedule throughout the month of March:

March [...]

Continue Reading