Construction Update | March 30-April 8

On Ellis Street, crews are excavating this shaft to perform ground improvements. During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in Chinatown or North Beach. Descriptions of construction impacts in each neighborhood are available here or at the […]

Continue Reading

22 March 2013 ~ 0 Comments

Construction Update | March 23-April 1

At the site where tunneling will begin, crews have started to build a floor known as a mud slab on the bottom of the excavation. During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in Chinatown or North Beach. […]

Continue Reading

19 March 2013 ~ 1 Comment

Questions about construction in North Beach? Check out these FAQs.

The Central Subway tunnels will end here, at the Pagoda Palace in North Beach, under a plan to relocate the retrieval site for the project’s tunnel boring machines. In response to community concerns about Central Subway construction in North Beach, SFMTA staff and multiple city agencies have worked for the past few months to relocate […]

Continue Reading

15 March 2013 ~ 0 Comments

Construction update | March 16-25

At Union Square, the contractor is continuing to construct below-ground walls in preparation for tunneling. During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in Chinatown or North Beach. Descriptions of construction impacts in each neighborhood are available here […]

Continue Reading

08 March 2013 ~ 0 Comments

Construction update | March 9-18

A covered walkway has been installed on Stockton Street next to the site where crews are installing underground walls. During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in Chinatown or North Beach. Descriptions of construction impacts in each […]

Continue Reading

07 March 2013 ~ 1 Comment

Introducing Big Alma and Mom Chung, the Central Subway’s tunnel boring machines

  Mom Chung, shown here, will construct the tunnel for southbound trains. More photos of both TBMs are available on our Flickr page. (Photo courtesy of The Robbins Company) We are excited to introduce Big Alma and Mom Chung, the tunnel boring machines (TBMs) that will excavate and construct the Central Subway tunnels. Named Big […]

Continue Reading

05 March 2013 ~ 0 Comments

North Beach update: Board of Supervisors approve key component of TBM retrieval relocation plan

The Central Subway tunnels would end here, at the Pagoda Palace in North Beach, under a plan to relocate the retrieval site for the project’s tunnel boring machines. The Board of Supervisors today voted unanimously to pass a key component of the plan to relocate the retrieval site for the Central Subway’s tunnel boring machines […]