Archive | Traffic

05 November 2015 ~ 0 Comments

Heads up – 4th and King Track Work

Starting at 10pm tomorrow Friday November 6th work will begin at the intersection of 4th and King to install a new track configuration for the future surface portion of the T Third Line extension through South of Market.  Starting November 6, work will last for eight days, finishing on November 14.  This work will temporarily affect both pedestrians and […]

Continue Reading

03 September 2015 ~ 0 Comments

Labor Day Weekend Trackwork

The summer of 2015 is coming to a close with a brunch of activity! The San Francisco Municipal Transportation Agency (SFMTA) is focused on projects that will make transportation safer and more reliable. In addition, BART will be shutting down the Transbay Tube for weekend track repairs. And Billy Joel is in town for a […]

Continue Reading

03 August 2015 ~ 2 Comments

Upcoming work at 4th and King

Heads up! Construction work at 4th & King is slated for Labor Day Weekend, September 4 through 7. This will be a two-phase project for signal installation and track enhancement. Below is the area where work will take place. Over the Labor Day Weekend, the T Third Line rail service will still run, but Muni […]

Continue Reading

25 July 2014 ~ 0 Comments

Project Advancements | July 26 – August 4, 2014

During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates about what is happening in each neighborhood. For more detailed information click here or on the links below. You can also find construction, traffic detour, and Muni impact information on our […]

Continue Reading

18 July 2014 ~ 0 Comments

Project Advancements | July 19 – July 28, 2014

During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates about what is happening in each neighborhood. For more detailed information, click here or on the links below. You can also find construction, traffic detour, and Muni impact information on our […]

Continue Reading

11 July 2014 ~ 0 Comments

Construction Update | July 12 – July 21, 2014

During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This post contains brief updates about what is happening in each neighborhood. For more detailed information, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project […]

Continue Reading

03 July 2014 ~ 1 Comment

Construction Update | July 04 – July 14

Now that tunneling is complete, the TBM “Big Alma” is being prepped for removal. During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This post contains brief updates about what is happening in each neighborhood. For more detailed information, click here or on the links […]

Continue Reading

27 June 2014 ~ 0 Comments

Construction Update | June 28 – July 07

Starting July 1, Stockton Street between Post and Geary will be closed for one month to vehicular traffic. Please use alternate route and follow construction signs. During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This post contains brief updates about what is happening in […]

Continue Reading

07 December 2012 ~ 0 Comments

Construction update: Subsurface wall construction underway at new SoMa location; construction paused in Union Square, North Beach

The tunneling contractor has begun installing below-ground walls to prepare for tunneling at this site on 4th Street between Howard and Folsom streets. Since our last update, construction in Union Square and North Beach has paused for the holiday season, while work at two sites in SoMa has continued to move forward. In addition, work […]

Continue Reading

26 November 2012 ~ 0 Comments

Photos: Union Square, North Beach construction sites restored for holiday season

Last week Central Subway crews restored portions of Stockton Street and Ellis Street in Union Square and Columbus Avenue in North Beach to prepare for a holiday season construction pause. On these blocks, roadways and pedestrian walkways were returned to their regular use in time for Thanksgiving. Check out these photos of restoration in progress […]

Continue Reading