Project Advancements | February 21 – March 2

Workers install waterproofing and build temporary wooden forms before pouring concrete for the new interior walls of the tunnel portal.

Workers install waterproofing and build temporary wooden forms before pouring concrete for the new interior walls of the tunnel portal.

This post contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern SoMa, Union Square, Chinatown and North Beach over the next two weeks. For more detailed information, click here or on the links below. You can also find construction, traffic detour, and Muni impact information on our project Google Map.

Construction schedules may change due to unforeseen conditions. We encourage the public to follow traffic and pedestrian notifications posted at the work sites.

Southern SoMa (Harrison to King): Utility work along 4th Street from Harrison to King streets. Portal construction on 4th Street between Harrison and Bryant streets.

Northern SoMa (Market to Harrison): Excavation and construction of station roof along 4th Street between Howard and Folsom streets. Ongoing ground improvement activities at 4th and Jessie streets.

  • Utility work on Folsom Street at 4th Street
    • Two traffic lanes available on Folsom Street during work hours of 9 p.m. to 5 a.m.

Union Square: Excavation of the station, relocation and supporting of utilities on Stockton Street between Ellis and Post streets.

Chinatown: Excavation of the site and preparation for the installation of the station roof.

  • Sewer upgrade starting Feb. 23 on Stockton Street between Washington and Jackson streets
    • Parking lanes on both sides of Stockton Street will be used for travel lanes from 9 a.m. to 3 p.m.

North Beach: Work in front of 1731-1741 Powell Street (retrieval shaft) is anticipated to finish by the end of February. Hours of work are 7 a.m. to 4 p.m. A lane of traffic will be available on Powell Street.

  • Sidewalk restoration is slated for completion by the end of Feb.
  • Street light installation may start by the end of Feb.

We thank the businesses, residents, shoppers, and commuters of San Francisco for their continued engagement with this significant investment in the extension of our public transportation system. When opened in 2019, the Central Subway will provide a much-needed connection between major employment, retail, cultural and residential areas of the city.