Project Advancement | June 26 – July 6

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Construction schedules, bus […]

Continue Reading

25 June 2015 ~ 0 Comments

Featured Photos – June 25

No. It’s not a swimming pool. But it is water-proofing of the new roof slab for the future Yerba Buena | Moscone Station. Next steps for the roof deck include an additional layer of concrete and the installation of utilities. Sections of rebar, currently capped with bright orange markers, reinforce brackets that will support utility […]

Continue Reading

19 June 2015 ~ 0 Comments

Project Advancements | June 19 – 29

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Construction schedules, bus […]

Continue Reading

18 June 2015 ~ 2 Comments

Featured Photos – June 18

As part of the ancillary utilities work for the Central Subway, the Contractor is paving 4th Street at Bluxome following the upgrade of a 78″ sewer line. Pictured below is the bottom half of the sewer line before installation of a reinforced concrete roof designed to support the weight of passing light rail vehicles. Triton […]

Continue Reading

12 June 2015 ~ 0 Comments

Project Advancements | June 12-22

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment.  You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown. Construction schedules, bus […]

Continue Reading

11 June 2015 ~ 0 Comments

Throwback Thursday – June 11, 2015

Early 2013 aerial view of former mixed-use business and residential building at Stockton and Washington streets. The Chinese Historical Society of America and Students from the Chinatown YMCA contributed artwork for the building wrap design that promoted the future entrance to the Chinatown Subway Station. Toward the end of 2013, building demolition was completed and […]

Continue Reading

05 June 2015 ~ 0 Comments

Project Advancements | June 5-June 15

We made some changes to our weekly construction update. This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment.  You’ll find work activities, traffic and transportation impacts over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square […]

Continue Reading

04 June 2015 ~ 0 Comments

Featured Photos – June 4

Surface demolition is well underway. Construction crews prepare to excavate a portion of the Union Square Garage for the northern entrance to the future Union Square/Market Street Station. Benches, railings (shown in the lower portion of this photo) and planters have been removed from the south east corner of the park. After roof work, construction […]

Continue Reading